Construction of a complete gold processing facility including a run-off mine hopper, primary crushing, secondary crushing and 5-kilometre overland conveyor.
We also installed a complete processing plant at the end of the overland conveyor which included a stockpile, reclaim 1 large grinding mill, a regrind mill, 12 leach tanks, 5 thickeners, a flotation circuit, a reagents plant, a lime plant, oxygen plant, a gold room as well as 37 kilometres of interconnecting piping
This project was constructed in the highlands of Papua New Guinea, expending over 1,500,000 hours on-site LTI-free.
Client: Harmony Gold
Project Value: $55,000,000.00
Date Completed: 2008